Experience      - Project Executed

 

 

 

 

 

 

 

 

 

 

CLIENT

PROJECT

DATE OF COMPLETION

Consultant/ Remarks

Reliance Energy Limited, Mumbai.

Design, engineering, manufacture, supply, erection, commissioning of Integral coal handling system for 2 X 300 MW DCR Thermal Power Project at Yamunanagar, Haryana with wagon tippler, stacker cum reclaimer, crusher, conveyors, sampling system, online analyzer etc. structural, electrical  instrumentation work.

Dec 2007

Desein Limited, New Delhi

Bhushan Steel & Strips Ltd., New Delhi.

Design, engineering, manufacture, supply, erection and commissioning of Raw Material handling system including mechanical and structural work for the Integrated Steel plant at Meramandali, Orissa.

1) Design, engg, manufacture, supply supervision of E & C of two Nos of roll crushers for handling char in DRI plant

2) Raw Material Handling System having belt conveyors, vibro-feeders, apron feeders, belt feeders, Belt scales, trippers, gates, chutes etc

 

 

 

December 2005

 

 

April 2005

MECON, Ranchi

-do-

Design, engineering, manufacture, supply, erection and commissioning of Material handling system for DRI package consisting of belt conveyors, vibro-feeders, apron feeders, belt feeders, Belt scales, trippers, gates etc.

March 2006

MECON, Ranchi

-do-

Design, engineering, manufacture, supply, erection and commissioning of Material handling system for SMS charging system.

July 2007.

MECON, Ranchi

Grasim Industries Ltd., Mumbai

Design, engineering, manufacture, supply of belt conveyor system consisting of 80 nos of belt conveyors of total length approx. 12km for Cement plant at Aditya Cement, Unit-II at Shambhupura, Rajasthan

July 2008

Holtec, Noida

UltraTech Cement Ltd, Mumbai

Design, engineering, manufacture, supply of belt conveyor system consisting of 88 nos of belt conveyors of total length approx. 9.7km for Cement plant at Andhra Pradesh Cement Works, Unit-II at Tadipatri, AP

July 2008

Holtec, Noida

Grasim Industries Ltd., Mumbai

Design, engineering, manufacture, supply of belt conveyor system consisting of 20 nos of belt conveyors of total length approx. 0.8km for cement plant at Birla Plus Cement, Panipet, Haryana

June 2008

Holtec, Noida

Rourkela Steel Plant (M/s. Steel Authority of India)

Design, engineering, manufacture and supply of stock house conveying and screening system incl. Civil, mechanical, structural and electrical work.

June 2005.

CET, Ranchi

IISCO plant (Steel Authority of India Ltd.)

Design, engineering, manufacture, supply, erection and commissioning of Stockhouse system for Blast Funace-2 for IISCO, Burnpur.

Dec 2008.

CET, Ranchi

JSW Steels Ltd., (Jindal Vijayanagar Steel Ltd.,) Bellary

Design, engineering, manufacture, supply, site fabrication, erection, commissioning of conveyors including structural work, for Sinter Raw Material handling System for expansion project.

August 2006.

 

JSW Steels Ltd., (Jindal Vijayanagar Steel Ltd.,)

Bellary

Design, engineering, manufacture, supply, site fabrication, erection, commissioning of conveyors including structural work, for Sinter Raw Material handling System for expansion project.

May 2007

MECON, Ranchi

JSW Steels Ltd., (Jindal Vijayanagar Steel Ltd.,) Bellary

Design, engineering, manufacture, supply, supervision of erection, commissioning of belt conveyors and high angle conveyors for the EOF HMPT handling System.

June 2007

MECON, Ranchi

Bhilai Steel Plant    (M/s. Steel Authority of India,)

Design, engineering, manufacture, supply, erection, commissioning of conveyors, screens including civil, structural, electrical work, modification of equipment for Stock House Eqpt under revamping & upgradation of BF-7

February 2007

CET, Ranchi

Videocon Narmada Glass, Bharuch

Design, engineering, manufacture and supply of conveying system incl. mechanical, structural and electrical work.

March 2006

MN Dastur & Co (P) Ltd, Mumbai.

Upper Ganges Sugar & Inds. Ltd., UP

Design, engineering, manufacture and supply of bagasse and ash handling system for the 22 MW Cogeneration power plant.

Phase -1 & 2 commissioned.

 

Jaykaycem Ltd. (Subsidiary of JK. Cement Ltd.,)

Design, Manufacture and Supply of 25 Nos. of Belt Conveyors to their New 6500 TPD Cement Factory in Muddapur (Karnataka)

Supply completed

 

Ispat Industries Ltd., Dolvi

Design, engg, manufacture and supply, erection & commissioning of conveying system for coke fines/ iron ore fines/ sinter.

March 2006

MN Dastur & Co (P) Ltd, Kolkata

Ispat Industries Limited, Dolvi

Design, manufacture, supply of Blast furnace Return Fines conveyor systems at the Sinter plant.

June 2007

MN Dastur &CO., Kolkata

Grasim Industries Ltd.,  for M/s. RAJASHREE CEMENT MALKHED  KARNATAKA

 

Design, engineering, manufacture and supply of conveying system incl. mechanical, structural and electrical work. incl.

1) Modification of existing CHP incl. supply of crusher of 210 TPH, flip flow screens - 2nos of 130TPH, belt conveyors along with DE system etc.,

2) Extension of stockpile conveyors- 4 nos for stackers/ Reclaimers and CRDs for the same.

May 2008.

TCE Consulting Engineers Ltd., Bangalore.

 

Vasavadatta Cement, Hyderabad

Design, engineering, manufacture, supply, supervision of erection and commissioning of

a) Conveyor system for in-plant material handling system for cement plant expansion project-III at Sedam unit and coal stockyard conveyors

b)  Belt conveyors of 1400 TPH capacity for handling limestone from limestone from mines to new stacker

 

 

September 2006

 

-do-

 

Hindalco Industries Ltd., Kolkata

Design, engineering, supply, fabrication, erection and commissioning of  conveyors, feeders, DE, structure, electrical and instrumentation for the 2 X300 TPH coal handling system for the 100 MW CPP Unit-4 at Hirakud.

May 2008.

Development Consultants (P) Ltd, Kolkata

Dalmia Cement (Bharat) Ltd., Dalmiapuram, TN

Design, engineering, manufacture, supply& supervision of erection & Commissioning of belt conveying system for material handling system for New Cement Plant

March 2006

Consultants: M/s. Holtec Consulting Pvt Ltd, New Delhi.

Dalmia Cement (Bharat) Ltd., Dalmiapuram, TN

Design, manufacture, supply of Coal Screen System of 150 TPH capacity for screening coal of (-) 10mm and (-) 6mm for Cement/ Power plant.

March 2008

 

Chamundeswari Sugars Ltd, Bangalore

Design, engineering, manufacture and supply of bagasse coal and ash handling system for the 22 MW Cogeneration power plant.

May 2008.

Avant Garde Engg.     & Consultants (P) Ltd., Chennai.

Madras Cements Ltd., Jayanthipuram AP

Design, engineering, manufacture, supply of 26 nos of  belt conveyors of capacity upto 1400 TPH for crusher, raw mill, coal handling and modification of existing system

April 2008.

 

Jindal Steel & Power Ltd. Raigarh

 

Design, engineering, manufacture and supply of screening system for SMS-II plant incl. 24 conveyors and 6 screens.

Design, engineering, manufacture and supply of components for round caster in Unit-II plant.

June 2005

 

July 2005

Singh Associates, New Delhi

GMR Inds Limited, Hyderabad

Design, engineering, manufacture and supply of bagasse coal and ash handling system for the 22 MW Cogeneration power plant.

April 2008.

Avant Garde Engg.     & Consultants (P) Ltd., Chennai.

Rajshree Sugars & Chemicals Ltd, Coimbatore

Design, engineering, manufacture, supply, erection and commissioning of bagasse and ash handling system for 22 MW Cogeneration plant at Mundiampakkam, TN.

April 2005

 

Avant- Garde Engineers & Consultants (P) Ltd, Chennai

Thermax Ltd, Pune

Design, engineering, manufacture, supply, erection and commissioning of Fuel handling system for M/s. Arasmeta Power Co. Pvt Ltd., Chattisgarh.

April 2006

 

Thermax Ltd, Pune

Design, engineering, manufacture, supply, erection and commissioning of Fuel & Limestone handling system  for 2 X 18.5 MW CPP of M/s. Madras Cements Ltd., TN.

March 2005

 

Thermax Ltd, Pune

Design, engineering, manufacture, supply, erection & commissioning of Fuel handling system for M/s. Madras Cements Ltd at Jayanthipuram AP.

July 2007

 

Thermax Ltd, Pune

Design, engineering, manufacture, supply, erection and commissioning of Fuel handling system for Dwarakesh Energy Ltd., Rajasthan (JK Lakshmi Cement )

March 2005

 

Nandi Sahakari Sakkare Karkhane Niyamit, Bijapur Dist.

Design, engineering, manufacture, supply, erection and commissioning of bagasse and ash handling system for 18.1 MW Cogeneration plant.

September 2005.

JP Mukherjee & Associates, Pune

ITC Ltd., PSPD. Hyderabad

Design, engineering, manufacture, supply, erection and commissioning of Fuel handling system for Coimbatore unit.

June 2005.

TCE Consulting Engineers, Bangalore.

ITC Limited, PSPD, Hyderabad

Design, engineering, manufacture, supply of six nos of belt conveyors for Lime mud and Burnt lime handling system.

May 2008.

SPB-PC

Paul Wurth India (P) Ltd, New Delhi

Design, engineering, manufacture, supply of conveyors for Granulated Slag System for M/s. Tata Steel Ltd., Jamshedpur.

April 2008.

 

My Home industries Ltd, Hyderabad

Design, engineering, manufacture, supply, erection and commissioning of 24 nos belt conveyors for Cement plant

June 2006

 

Sakthi Sugars Ltd. Coimbatore

Design, engineering, manufacture and supply of bagasse and ash handling system for the 22MW Power Plant at Sivaganaga.

May 2008.

Avant Garde Engg.     & Cons (P) Ltd., Chennai.

Viraj Steel & Energy Ltd., New Delhi

Design, engineering, supply, fabrication, erection and commissioning of raw material handling system consisting of 37 nos of belt conveyors, tripper conveyors etc., for the 2 X 350 TPD sponge iron plant

July 2006

Predominant Engineers & Contractors (P) Ltd., New Delhi.

Soma Enterprises Ltd. New Delhi

Design, engineering,, manufacture, supply, of conveyor, electricals supervision of fabrication, erection and commissioning of 1200 TPH aggregate handling conveyor for Subansiri Lower hydroelectric project.

July 2006

 

Maa Mahamaya Industries Pvt Ltd., Vizag

Design, engineering, manufacture, supply, site fabrication, erection and commissioning of conveyor system for RMHS for 350 TPD sponge iron plant.

March 2006.

Predominant Engineers & Contractors (P) Ltd., New Delhi.

Italcementi S.p.A, Italy

Rails and accessories for the stacker and reclaimer for the cement plant expansion project.

June 2008.

 

BSES Limited, New Delhi,

Design, engg, manuf., supply, erection and comm. of coal/ lignite handling system for the 12.5 MW CPP at Ariyalur, TN for Grasim Cements Ltd.

June 2003.

Avant-Garde Engineers (P) Ltd/  Holtec Consulting Pvt .Ltd

Vandana Global Limited., Raipur

Design, engineering, manufacture, supply, fabrication, erection and commissioning of coal handling system for 33MW CPP.

July 2007.

MN Dastur & Co (P) Ltd, Chennai.

Action Ispat & Power (P) Ltd., New Delhi

Design, engineering, supply, of Material Handling System for 350 TPD sponge iron plant at Jharsuguda.

March 2006.

 

Metso Minerals Pvt. Ltd, New Delhi

Design and engineering, supply, fabrication of conveyor structures and conveyor components.

Different Schedules.

For road construction projects.

Southern Iron and Steel Co. Ltd., Salem

Design, Engg. manuf., supply, supervision of erection and comm. of conveyor system for coke oven and blast furnace project for the steel plant expansion project.

November 2006.

MECON Ltd., Bangalore.

Monnet Ispat Limited, New Delhi.

Design, Engg. manuf., supply of conveyor system for RMHS for the iron ore and coal handling for the 4 X 350 TPD/2X 100 TPD Sponge iron plant.

October 2006

 

Bhilai Steel Plant (M/s. Steel Authority of India Ltd.)

Design, engg, manufacture, supply, Erection and commissioning of conveying, crushing and screening plant of Oversize Iron ore lumps at Dalli Mechanised Mines.

March 2006

CET, Ranchi

Grasim Industries Ltd., Cement Division

Design, engg, manufacture, supply & supervision of erection & Commissioning of belt conveying ­­­system for Limestone conveying from Mines to plant 1300 TPH, Additives conveying to Raw mill 250 TPH & limestone conveying from stockpile to Cement Mills 250 TPH. for M/s. RAJASHREE CEMENT,  KARNATAKA

July 2004

Bhagwati Designs Pvt Ltd, Hyderabad

Grasim Industries Ltd., Cement Division

Design, engg, manufacture, supply & supervision of erection & Commissioning of belt conveyors for Limestone conveying from Mines to plant @ 1400 TPH. for   M/S. VIKRAM CEMENT, NEEMUCH, M.P.

May 2004

HOLTEC Consulting Pvt Ltd., New Delhi

-do-

Design, engg, manuf, supply supervision of erection & Commissioning of pre-screening belt conveyor for Thermal power plant at Aditya Cement.

May 2005

 

Grasim Industries Ltd., Cement Division

Design, engg, manufacture, supply& supervision of erection & commissioning of belt conveying system for coal washery plant at Raipur.

Commissioned

 

Grasim Industries Ltd., Cement Division

Design, engg, manuf, supply supervision of erection & Commissioning of belt conveyor, feeder, tripper and retrofitting of Gypsum Storage & Reclamation system at Birla Plus Cement, Bathinda.

Supply completed.

 

HOLTEC Consulting Engg. New Delhi.

-do-

Design, engg, manufacture, supply & supervision of erection & commissioning of belt conveying system for Limestone conveying to power plant.

March 2005.

 

-do-

Design, engg, manuf, supply of coal, slag and gypsum handling conveyors for Cement plant at Raipur.

June 2006.

 

-do-

Design, engg, manuf, supply, supervision of erection & Commissioning of 9 nos of conveyors upto capacity of 1200 TPH of clinker/ gypsum for One MTPA Dadri grinding unit at Dadri, UP.

May 2008.

HOLTEC Consulting Engg. New Delhi.

UltraTech Cement Ltd., Mumbai

Design, engg, manuf, supply supervision of erection & Commissioning of 4 nos of conveyors for handling biomass and shredded tyre for the Gujarat unit.

Supply completed.

 

UltraTech  Cement Ltd. Mumbai

Design, engineering, manufacture, supply of belt conveyor system of 18 nos of belt conveyors for Ginigera Grinding Unit at Koppal Karnataka.

Supply completed.

 

UltraTech  Cement Ltd. Mumbai

Design, engineering, manufacture, supply of belt conveyor system of 17 nos of belt conveyors for Hirmi Cement Works, Chattisgarh.

Supply completed.

 

EEL India Ltd, New Delhi

Design, engineering, manufacture of 64 nos of belt conveyors for Grasim Panipat, Shambhupura, Kotputli, Ginigera and UltraTech-Tadipatri units for the packing plant along with spiral chutes, liners.

April 2008.

 

Chettinad Cement Corpn. Ltd, Chennai

Design, engineering, manufacture, supply. Erection and commissioning of coal handling plant for 15MW CPP at Karikkali.

Oct 2004

Avant-Garde Eng & Cons (P) Ltd & Holtec Consulting Pvt Ltd.,

Chettinad Cement Corpn. Ltd, Chennai.

Design, Manufacture and Supply of coal handling system for the CPP at Puliyur Works.

April 2008.

Avant Garde Engg.     & Cons (P) Ltd., Chennai.

Chettinad Cement Corpn. Ltd, Chennai.

Design, Manufacture and Supply of 38 Nos. of Belt Conveyors to their New 2 MTPA Cement Factory at Ariyalur.

Dec 2008

Holtec Consulting Pvt Ltd.,

Chettinad Cement

Corpn. Ltd, Chennai.

Design, Manufacture and Supply of coal handling system for the CPP Works for their New 2 MTPA Cement Factory at Ariyalur.

August 2008

Avant Garde Engg.    & Cons (P) Ltd., Chennai.

RAS Cement (Shree Cements Ltd) Rajasthan

Design, engineering, manufacture, supply & supervision of erection of Conveying system for 3000 TPD Cement plant at RAS, Rajasthan

Design, engineering, manufacture, supply & supervision of erection of Conveying system for 3000 TPD Cement plant at RAS, Rajasthan

June 2005

 

July 2005

 

Jaiprakash Associates

Ltd. New Delhi

Design, engineering, manufacture , supply of Coal handling Plant Package-1 for Rewa CPP-3

Sept 2008

 

Coal Handling Plant Package (35 MW) for their Unit at Sidhi.

Sept 2008

 

Coal Handling Plant Package (27 MW) for their Unit at Dalla.

Sept 2008

 

Coal Handling Plant Package (27 MW) for their Unit at Chunar

Dec. 2008

 

Mangalam Cement Ltd. Kota

Design, engineering, supply of coal and Petcoke handling system including Crushers, vibrating and flip flow screens for 17.5MW CPP at Kota.

August 2007

 

Seshasayee Paper & Boards Ltd., Erode.

Design, engineering, manufacture, supply& supervision of erection  of coal/ lignite handling system for 20 MW CPP

Nov 2004.

SPB-PC Ltd., Chennai

Utkal Manufacturing & Services Ltd., Orissa.

Design, engg, manufacture, supply, erection & Commissioning of Material handling system including screens & feeders for Ferro Chrome plant at Choudwar.

March 2006

 

NTPC Limited, Talchar TPS

Design, manufacture, supply of four nos of trippers with chutes, walkways, platform etc, flap gate with actuator, pulleys, idlers brake Drive etc.

July 2007.

 

Jaiprakash Associates Ltd. N. Delhi

Design, engineering, manufacture, supply, supervision of erection and commissioning of coal handling plant for 38.5 MW CPP-III at Rewa (MP).

April 2006.

 

-do-

Two nos of belt conveyors with DE system.

June 2006.

 

Om Shakthi Renergies Limited, Hyderabad

Fuel and Ash Handling system for 6 MW Biomass based Power project at Chittor, AP

Nov 2003.

MN Dastur & Co., Chennai.

India Gypsum Ltd., Bangalore

Design, engineering, manufacture, supply, erection and commissioning of the Raw material conveying system for the Plaster board unit

 

 

Sangam Spinners Ltd, Bhilwara, Rajasthan

Design, Engg., manuf., supply, erection and comm. of coal/ lignite/ Petcoke/ limestone handling system for 7.5 MW CPP

Oct 2003.

MN Dastur & Co., Chennai.

Sangam Spinners Ltd, Bhilwara, Rajasthan

Design, Engg., manuf., supply, erection and comm. of Ash handling system for 7.5 MW CPP

Nov 2003.

 

Nova Petrochemicals Limited, Ahmedabad

Design, Engg. manuf., supply, erection and comm. of coal, pet coke, limestone and groundnut shell handling system for 7.5 MW CPP.

August 2003.

MN Dastur & Co., Chennai.

M/s. Stallion Engg. Systems Ltd., New Delhi.

 

Design, engineering, manufacture, supply& supervision of erection of 13 Nos of belt conveyors for coal handling upto 400 TPH.

March 2005.

 

Design, engineering, manufacture, supply& supervision of erection of belt conveyors for coal handling upto 400 TPH for Dipka project.

April 2005.

 

Stallion Engg Systems Ltd., New Delhi.

Design, engineering, manufacture, supply& supervision of erection of belt conveyors for coal handling upto 300 TPH for Dipka project.

March 2005.

 

SMC Power Generation Ltd. New Delhi.

Design, engineering, manufacture, supply& supervision of erection of Raw material handling system for Integrated Steel plant at Hirma, Jharsuguda, Orissa.

Jan 2005.

Predominant Engineers, New Delhi

B. Seenaiah & Co (Projects) Ltd, Hyderabad.

Design, Engg. manuf., supply, erection and comm. of biomass (rice husk, bagasse, Julie flora) and coal handling system for 7.5 MW Power plant.

Oct 2003.

MN Dastur & Co., Chennai.

Stallion Engg Systems (P) Ltd. New Delhi.

Design, engineering, manufacture and supply of conveyor system for handling coal of capacity upto 500 TPH

Design, engg, supply of conveyor system for coal washery.

March 2004.

Civicon Engineers

Sterlite Inds. Ltd., Tuticorin.

Design, engg, manufacture and supply, fabrication and erection and commissioning of Flux conveyor system.

September 2005.

 

Khanna Paper Mills Ltd., Amritsar.

Design, engg, manufacture, supply, erection & commissioning of coal handling plant for cogen and power plant.

Dec 2004.

 

Jayaswals Neco Ltd, Raipur.

Design, engg, manuf., supply, erection and comm. of Coal handling plant for 18MW CPP for the steel plant at Raipur (Chattisgarh)

June 2003.

MN Dastur & Co., Kolkata

Additional requirement of system for above CHP.

-do-

 

Tamil Nadu Newsprint & Papers Ltd, Karur.

Bagasse handling system and Pith handling at Thuhili site.

Dec. 2003.

Avant-Garde Engineers & Consultants (P) Ltd,

OCL India Limited., New Delhi

Design, engineering, manufacture, supply, erection and commissioning of Belt conveyors for handling clinker, coal, gypsum and slag for New Grinding unit at OCL, Kapilas Road, Orissa.

May 2008.

Holtec Consulting (P) Ltd, New Delhi

OCL (India) Ltd,  Rajgangpur Orissa

Design, engineering, manufacture, supply & supervision of erection of 20 Nos of belt conveyors for CVRM-3 project.

September  2005

 

Design, engg, supply of belt conveyors for cement plant.

Completed.

 

Design, engg, supply of belt conveyors for bagging plant.

Completed.

 

Global Coal & Mining (P) Ltd. Talchar, Orissa.

Design, engg, supply of conveyors for coal washery at Talchar Mines.

Completed

 

Design, engg, supply of conveyors for coal washery at Talchar Mines.

Completed

Repeat order

Global Coal & Mining (P) Ltd. Talchar, Orissa.

Design, engg, supply of conveyors for coal washery.

Completed.

Second repeat order

Supply of five nos of belt conveyors for the coal washery at Jharsuguda, Orissa.

Completed.

Fourth order in 3 years.

Supply of one belt conveyor for Talchar plant.

Completed.

Fifth order.

Aarthi Steels Ltd., Cuttack.

Design, engineering, manufacture, supply & erection of material handling system for DRI storage & Furnace Handling system.

June 2006.

 

Meghalaya Cements Ltd., Kolkata.

Design, engineering, manufacture, supply& supervision of erection of 15 Nos of belt conveyors for Lumshnong project.

Nov 2005

Holtec Consulting Pvt Ltd, New Delhi & Hallmark, Pune.

Century Pulp & Paper, UA.

Design, engineering, manufacture, supply, erection and commissioning of 4 Nos of belt conveyors for wood chip handling.

Dec 2005

 

Chitrakoot Steel & Power Ltd, Chennai

Supply of conveyor components and equipment viz., crushers, screens feeders for 100 TPD sponge iron plant.

Dec 2005

 

Loesche India Pvt Ltd., New Delhi.

Design, engineering, manufacture, supply of belt conveyors for Nigeria Project.

February 2006